Water Sump & Tank Estimator: Capacity, RCC & Cost Guide

Views in the last 30 days: 13

Estimated read time: 5 minute(s)

Water-Sump / Tank Calculator — Capacity, Materials & Cost (Instant)

This interactive calculator sizes your **rectangular or cylindrical** water tanks, computes **storage capacity**, estimates **concrete**, **rebar**, and **waterproofing**, and builds a **cost summary** with editable rates for **India / US / UK**. It supports **multi-compartment** sumps, **SI / Imperial** units, **reverse mode** (size from target volume), **standards presets** (IS 3370, IS 456, ACI 350, BS 8007), and a **printable HTML report** with KPIs and a detailed table.

How it works (in plain language)

  • Geometry: Choose shape → enter inside dimensions (L, B, H) and freeboard. Reverse mode lets you enter a target capacity and it solves the height.
  • Materials: The tool derives base slab, walls, and top slab concrete volumes; planner-level rebar densities are prefilled by standard profile and are **user-editable**.
  • Waterproofing: Select internal/external/both sides; overlaps are included via a % allowance.
  • Costing: Enter local unit rates (auto-prefilled by country). A markup % applies to the materials subtotal.
  • Report: One click generates a clean, printable HTML report with project metadata, KPIs, breakdown table, assumptions, and formulas.
Note: This is a planning-level estimator. For reinforcement detailing, use your design outputs/BBS. For concrete mixes and covers, follow your project specifications and codes.

When to use this

  • Estimating **underground sumps** for buildings, villas, and campuses.
  • **Overhead tanks** with rectangular compartments (supports top slab).
  • Quick checks during design development, BOQs, and tender support.

Useful companions

Concrete mixes & multi-element BOQ → Concrete Calculator
Rebar cutting lists → BBS Calculator
Site grading/backfill → Cut-&-Fill Calculator
Inlet/outlet headloss → Pipe Design Calculator

Codes & Standards (presets)

  • IS 3370 (with IS 456) – default for India
  • ACI 350 – environmental engineering concrete structures
  • BS 8007 – liquid-retaining structures (legacy/UK)

“Values derived from <Standard> (user must verify)” – the tool pre-fills practical rebar densities and typical thickness heuristics but **does not** replace structural design.

Step-by-step: Sample project (complete)

Goal: Underground RCC rectangular sump for an apartment block, target capacity ≈ 40,000 L, internal L:W = 2:1, freeboard 150 mm. Location: Bengaluru (India), units: SI.

  1. Preset: Click “Underground RCC (Rectangular)”. Set reverse mode = “Given target capacity → find H”, enter 40,000 L, keep L=4.0 m, W=2.0 m, freeboard=0.15 m.
  2. Thickness (planning): Base 0.25 m, Walls 0.20 m, Top slab 0.15 m (edit per design).
  3. Rebar densities (IS 3370 profile): Base/Walls 110 kg/m³; Top 90 kg/m³.
  4. Waterproofing: “External (base+walls)”, overlap 10%.
  5. Rates (India defaults): Concrete ₹5,600/m³; Steel ₹70/kg; Waterproofing ₹500/m²; Markup 10%.
  6. Calculate: The tool computes capacity (≈40 kL), concrete volume, rebar weight, waterproofing area, and total cost. Open the HTML report for the printable breakdown.

FAQ

Can I size from litres/gallons? Yes—enable Reverse Mode and enter your target volume.

What about circular tanks? Choose “Cylindrical RCC” and enter diameter as “B”.

Does this cover excavation/backfill? Not directly; use the Earthwork calculator and add to your BOQ.

Water-Sump / Tank Calculator – Capacity, Materials & Cost

💧 Water-Sump / Tank Calculator

Capacity • Materials (RCC, Rebar, Waterproofing) • Cost • Multi-segment • SI/Imperial • Standards profile • Report
Global Settings
Defaults loaded from selected standard (user must verify).
Editable Unit Rates
Defaults based on indicative 2024–2025 public sources; edit for your city.
(per m³ in SI • per yd³ in Imperial)
(per kg in SI • per lb in Imperial)
(per m² in SI • per ft² in Imperial)
Applied to materials subtotal
Segments (Compartments)
Methodology & Formulas
Show derivations (units shown live)
Capacity (rectangular, internal): V = L × B × (H − freeboard) Capacity (cylindrical, internal): V = π × (D/2)² × (H − freeboard) Concrete: Base slab ≈ plan area × tbase; Walls ≈ perimeter × H × tw; Top slab (if any) ≈ plan area × ttop. Rebar estimate (planner level): 100–120 kg/m³ (walls & base) and 80–100 kg/m³ (top slab). Auto-filled by standard; user must verify by design/BBS. Waterproofing area: base + walls + top (if selected). Unit conversions: 1 m³ = 1000 L; 1 yd³ = 0.764555 m³; 1 ft = 0.3048 m; 1 lb = 0.453592 kg.
Standards preset note: Values derived from the selected standard profile (cover/coefficients heuristics), not a substitute for structural design. User must verify with IS 3370/IS 456/ACI 350/BS 8007 and project specs.
Calculated Results
Total Capacity
Concrete Volume
Steel Weight
Waterproofing Area
Update to see totals.