The engineering lab.

Explore the evidence. Test a change. Understand the result. Interactive tools for learning how source revisions, quantities and review decisions connect.

DRAWING → DIMENSIONS → QUANTITY → DECISION

Follow a quantity back to its source.

Select a base, compare two fictional revisions, then test a different depth. The drawing, calculation and quantity register stay connected.

EX-DWG-001 / R02

Fictional pump plinths P1–P4

P1 P2 P3 P4

P1 · L 2.000 m × W 1.500 m × D 0.300 m

Diagrammatic arrangement; not a setting-out drawing. All four bases share the same dimensions. Changing depth affects all four.

Try 0.35 m. Allowed range 0.10–1.00 m. Custom values are labelled WHAT-IF and do not change a source revision.

Calculation and quantity register

2.000 × 1.500 × 0.300 = 0.900 m³ per base

Same source and dimensions apply to P1–P4
BaseSourceQuantity (m³)
P1R020.900
P2R020.900
P3R020.900
P4R020.900
Total concrete volume3.600 m³
Variance against BOQ 3.800 m³−0.200 m³
Selected P1. R02 gives 3.600 m³. The BOQ is 0.200 m³ higher; record a query before issue.
R01 / 250 mm3.000 m³
→
R02 / 300 mm3.600 m³

Revision effect: +0.600 m³ across four bases. Assumptions: rectangular volume, no deductions, no wastage; reinforcement, formwork and excavation excluded. Variance = calculated − BOQ. Arithmetic is not engineering approval.

Read the complete BOQ method →

OBSERVE / QUESTION / EXPLAIN

Spot the discrepancy.

Three short practice cases. Look at the evidence, choose the best explanation, then reveal the reasoning.

Evidence on the desk

FICTIONAL TRAINING CASE

Current drawing R02: four bases, each 2.000 × 1.500 × 0.300 m. The takeoff still cites R01 (depth 0.250 m), and its quantity is 3.000 m³.

Review prompt

What should the reviewer investigate first?

No client documents or actual project results are used.

Choose the most likely discrepancy
Choose an answer to see the reasoning.

FIVE CHECKS / A CLEAR NEXT ACTION

What is missing before issue?

Record the state of your checks. This self-assessment identifies gaps; it does not certify a BOQ or replace responsible review.

0 of 5 checks recorded. Answer the questions to build your next-action list.

    Answers stay in this page until you reload or clear them. The optional text download is created locally in your browser. No account, project name or upload is required.

    PLAN / MEASURE / REPORT

    Turn quantities into a progress view.

    Compare planned and actual concrete volume at the same reporting cut-off. This is a single-item demonstration, not a weighted project dashboard.

    Reporting inputs

    Use the same scope, unit and cut-off for both figures. Measured quantities require their own evidence and acceptance. A quantity gap alone does not establish time delay or a completion forecast.

    Progress against total scope

    Planned50.0%
    Actual35.0%
    Actual is 6.000 m³ below plan: a −15.0 percentage-point gap against total scope.

    Bars show quantity ÷ total scope × 100. Gap = actual completion − planned completion, expressed in percentage points.